Ssemakula & Another v Attorney General
Ssemakula & Another v Attorney General (Civil Suit 616 of 2016) [2023] UGCommC 228 (29 March 2023)
The court found that the defendant, Uganda Police Force represented by the Attorney General, breached the contract by failing to pay the balance of the purchase price within the agreed time, deducting UGX 200,000,000 for alleged unfinished works without contractual authority, and failing to meet all tax obligations as expressly agreed in the contract. The court rejected the defendant's arguments regarding the plaintiffs' alleged breaches, noting that the addendum to the contract did not mention any outstanding obligations related to fencing, painting, or leveling the playground, and that the…
Source excerpt
- Breach Of Contract
- Land Sale Agreements
- Withholding Tax Disputes
- Remedies For Breach
- Contractual Obligations
- Damages