Planbuild Technical Services Limited v Attorney General (Civil Suit No. 1273 of 2023) [2025] UGCommC 136 (15 June 2025)
The court found that the dispute over retention monies and the issuance of the completion certificate arises from a determination made by the project manager, as evidenced by the letter from the Permanent Secretary, Ministry of Energy and Mineral Development. This determination falls squarely within the scope of the arbitration clause set out in GCC Clauses 24 to 25 of the contract. The arbitration clause is valid, operative, and capable of being performed with respect to the present dispute. The court is mandated by Section 5 of the Arbitration and Conciliation Act to refer such matters to a…
Source excerpt
- Arbitration Clause Scope
- Contractual Dispute Resolution
- Retention Money Claim
- Construction Contracts