Uganda
Sign in
Uganda Source-linked decisions Coverage checked

Uganda Case Law

Search judgments by proposition, citation, court, judge or legal topic, then move directly into the source-grounded case analysis.

Courts on this page
5 court collections
Last checked

Uganda decisions

Decisions matching the current search

Clear filters
Employment And Labour [2025] UGIC 43

Kamugisha Annette Magaiga (Administrator of the Estate of the Late Kamugisha Dennis) v Attorney General (Labour Dispute Claim No. 202 of 2014)

Kamugisha Annette Magaiga (Administrator of the Estate of the Late Kamugisha Dennis) v Attorney General (Labour Dispute Claim No. 202 of 2014) [2025] UGIC 43 (13 June 2025)

The court found that the Respondent breached the contract of employment by failing to pay the Claimant's statutory benefits within the prescribed period after retirement, as required by the Security Organisations (Terms and Conditions of Service) Regulations, 2000, and the Public Service Standing Orders. The 2000 Regulations applied to the Claimant's employment at the time of retirement, and subsequent amendments could not retrospectively deny accrued entitlements. The Claimant was entitled to outstanding gratuity, unpaid salary under the single spine salary structure, and leave allowance, as…

  • Terminal Benefits
  • Public Service Employment
  • Retirement Entitlements
  • Breach Of Employment Contract
  • Foreign Service Allowances
  • Interest On Awards
Read case analysis
Employment And Labour [2024] UGIC 65

Mawanda v Litespeed Job Hub Limited (Labour Dispute Reference 74 of 2023)

Mawanda v Litespeed Job Hub Limited (Labour Dispute Reference 74 of 2023) [2024] UGIC 65 (1 November 2024)

The Industrial Court found that failure to pay salary for three months amounted to constructive dismissal and awarded unpaid wages, damages and interest.

  • Constructive Dismissal
  • Unpaid Wages
  • Statutory Deductions
  • General Damages
  • Interest On Awards
  • Constructive-dismissal
Read case analysis
Employment And Labour [2024] UGIC 58

Musimenta v Equity Bank Uganda Limited (Labour Dispute Reference 187 of 2017)

Musimenta v Equity Bank Uganda Limited (Labour Dispute Reference 187 of 2017) [2024] UGIC 58 (11 October 2024)

The court found that the Claimant's loan was secured by a mortgage and not solely recoverable by salary deductions. Therefore, liability for repayment could not be shifted to the Respondent, even though the termination was unlawful. However, the Respondent was ordered to maintain the original concessional interest rate of 10% per annum, rather than the commercial rate imposed after termination. The court determined that the Respondent's conduct in terminating the Claimant without notice, reason, or hearing, and in refusing to provide a recommendation or certificate of service, was callous, op…

  • Unlawful Termination
  • Salary Loan Liability
  • Aggravated Damages
  • Certificate Of Service
  • Interest On Awards
Read case analysis
Land And Property [2024] UGHC 1261

Nampembe( Administrator of the estate of late kiwanuka) v Uganda Electricty Transmission Company Limited

Nampembe( Administrator of the estate of late kiwanuka) v Uganda Electricty Transmission Company Limited (Civil Suit 97 of 2023) [2024] UGHC 1261 (30 September 2024)

The Plaintiff proved lawful ownership of the suit land through letters of administration and certificate of title. The Defendant unlawfully entered and installed electricity transmission infrastructure without consent, constituting trespass. The Defendant's plea of res judicata failed due to lack of supporting evidence and absence of a final determination in the previous suit, which was withdrawn by consent. The Plaintiff is entitled to compensation for deprivation of use, as compulsory acquisition of land for public purposes requires prompt and fair compensation under the Constitution. The P…

  • Trespass To Land
  • Compulsory Acquisition
  • Compensation For Land
  • General Damages
  • Interest On Awards
Read case analysis
Tort Law [2023] UGHCCD 369

Serubiri(suing through his next friend Katende) v Umeme Limited (HC Civil Suit 469 of 2017)

Serubiri(suing through his next friend Katende) v Umeme Limited (HC Civil Suit 469 of 2017) [2023] UGHCCD 369 (6 September 2023)

The High Court of Uganda held Umeme Limited liable in negligence after an electrified falling pole injured a child, awarding general damages, interest, and costs.

  • Negligence
  • Duty Of Care
  • Breach Of Duty
  • Damages
  • Interest On Awards
  • Duty-of-care
Read case analysis
Tort Law [2023] UGHCCD 423

Serubiri v UMEME Limited

Serubiri v UMEME Limited (Civil Suit 469 of 2017) [2023] UGHCCD 423 (6 September 2023)

The Defendant, as a licensed distributor of electricity, owed a duty of care to the Plaintiff and the public to maintain its infrastructure safely. The Defendant breached this duty by failing to inspect and repair a rotten electricity pole, despite being reasonably expected to foresee the risk posed by loose live wires. The Defendant's failure to maintain and monitor its distribution infrastructure resulted in the Plaintiff's electrocution and severe injuries. The evidence established that the Defendant did not conduct regular maintenance or respond adequately to risks, and the Plaintiff's in…

  • Negligence
  • Duty Of Care
  • Breach Of Duty
  • Damages
  • Interest On Awards
Read case analysis
Employment And Labour [2023] UGCA 99

MTN (U) v Ndemirweki

MTN (U) v Ndemirweki (Civil Appeal No. 291 of 2016) [2023] UGCA 99 (17 March 2023)

The Court of Appeal partly allowed an employment appeal, upheld liability for unfair dismissal, reduced general damages, set aside exemplary damages, and lowered interest.

  • Unfair Dismissal
  • Wrongful Termination
  • Employment Contracts
  • Damages Award
  • Interest On Awards
  • Procedural Fairness
Read case analysis
Employment And Labour [2023] UGIC 31

Waiswa and 12 Others v Attorney General

Waiswa and 12 Others v Attorney General (Miscellaneous Application 26 of 2020) [2023] UGIC 31 (6 February 2023)

The Industrial Court confirmed UGX 571,843,006 as the applicants’ computed emoluments, rejected the full-payment claim for lack of proof, and ordered further proof of payment.

  • Terminal Benefits
  • Court Award Enforcement
  • Interest On Awards
  • Proof Of Payment
  • Affidavit Evidence
  • Employment-law
Read case analysis
Employment And Labour [2022] UGIC 21

Entebbe Handling Services T/a National Aviation Services (NAS) v Okello (Labour Dispute Miscellaneous Application No. 87 of 2022)

Entebbe Handling Services T/a National Aviation Services (NAS) v Okello (Labour Dispute Miscellaneous Application No. 87 of 2022) [2022] UGIC 21 (20 October 2022)

The Industrial Court corrected an arithmetical error in a labour award, substituting UGX 19,584,000 for UGX 22,074,741 and making no order as to costs.

  • Review Of Award
  • Arithmetical Error
  • Affidavit Requirements
  • Interest On Awards
  • Labour-law
  • Civil-procedure
Read case analysis
Commercial And Corporate [2022] UGCommC 20

Sanlam General Insurance (U) Ltd v Aya Investment (U) Ltd

Sanlam General Insurance (U) Ltd v Aya Investment (U) Ltd (Civil Suit No. 564 of 2020) [2022] UGCommC 20 (12 April 2022)

The High Court held that Aya Investment breached insurance contracts with Sanlam by failing to pay premiums, and awarded the outstanding sums, damages, costs, and interest.

  • Insurance Contracts
  • Breach Of Contract
  • Remedies For Breach
  • Interest On Awards
  • Insurance-contracts
  • Breach-of-contract
Read case analysis

About this JurisAssist collection

Uganda decisions are organised by court, judge, legal area and indexed issue so a practitioner can move from a proposition to a citable authority with the surrounding context intact.