Fort Portal Municipal Council v Plinth Technical Services Ltd
Fort Portal Municipal Council v Plinth Technical Services Ltd (Miscellaneous Application No. 231 of 2019) [2020] UGCommC 8 (20 March 2020)
The High Court held that arbitration was premature because the contract required adjudication first. It set aside the arbitrator’s jurisdiction ruling and stayed the arbitration.
- Arbitration Jurisdiction
- Contractual Dispute Resolution
- Adjudication Procedure
- Interpretation Of Contract Clauses
- Arbitration-jurisdiction
- Contractual-dispute-resolution