Petrol(u) Ltd v Sailesh Kumar Mambhai Patel (HCCS No. 696 of 2002) [2004] UGHC 61 (28 June 2004)
- Citation
- [2004] UGHC 61
- Status
- Judgment
- Jurisdiction
- Uganda
- Court
- High Court of Uganda
- Posture
- Civil Suit / Judgment
- Case number
- HCCS No. 696 of 2002
- Language
- English
More details
- Court
- High Court of Uganda
- Posture
- Civil Suit / Judgment
- Case number
- HCCS No. 696 of 2002
- Language
- English
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The plaintiff proved, through documentary and oral evidence, that it supplied petroleum products to the defendant under a dealership agreement and that the defendant failed to pay for two specific invoices. The defendant's absence and failure to adduce evidence meant the plaintiff's case was uncontroverted. The court found the claim valid and awarded the sum claimed, general damages for breach of contract, and interest. The defendant's counterclaim was dismissed for want of prosecution. The court exercised discretion to reduce the proposed general damages from Shs. 5 million to Shs. 3 million, considering the circumstances. Interest was awarded at 20% per annum on the liquidated sum and at court rate on general damages. Costs were also awarded to the plaintiff.
Court disposition
judgment_for_plaintiff
Orders
- The defendant shall pay the plaintiff Shs. 35,057,429.
- Interest on the above sum at 20% per annum from date of filing until payment in full.
- The defendant shall pay the plaintiff Shs. 3,000,000 as general damages.
- Interest on general damages at court rate from date of judgment until payment in full.
- The defendant shall pay the costs of the suit.
02
Material facts
Parties
Petro (U) Ltd
Plaintiff Counsel: Mr. KandeebeSailesh Kumar Mambhai Patel
Defendant Counsel: Mr. DhagiraAmounts and remedies
- Principal Sum Awarded: UGX 35,057,429
- General Damages Awarded: UGX 3,000,000
- Interest Rate on Principal: PERCENT 20
03
Procedural history
Posture
Civil Suit / Judgment
04
Questions and positions
Legal issues
- 01
Whether the money claimed by the plaintiff is due and outstanding.
- 02
What remedies are available to the parties.
Party arguments
- Applicant
- The plaintiff supplied petroleum products to the defendant under a dealership agreement. The defendant failed to pay for two invoices totaling Shs. 37,057,429, less a credit note of Shs. 2,557,571, resulting in a net claim of Shs. 35,057,429. The plaintiff made repeated demands for payment, which were ignored. The plaintiff seeks the outstanding sum, interest, general damages, and costs.
- Respondent
- The defendant denied liability and counterclaimed for Shs. 69,346,846, alleging various dealings. However, the defendant and counsel failed to appear at the hearing, and the counterclaim was dismissed for want of prosecution.
05
Court’s reasoning
Legal principles
- 01
Order 9 rule 19 of the Civil Procedure Rules
Where a defendant appears and the plaintiff does not appear when the suit is called on for hearing, the court shall make an order that the suit be dismissed, unless the defendant admits the claim.
- 02
General contract law principles; dealership agreement (Exhibit P1)
A party who fails to pay for goods supplied under a contract is in breach and liable for the outstanding sum, interest, and general damages.
06
Ratio, limits and disposition
Ratio decidendi
The plaintiff proved, through documentary and oral evidence, that it supplied petroleum products to the defendant under a dealership agreement and that the defendant failed to pay for two specific invoices. The defendant's absence and failure to adduce evidence meant the plaintiff's case was uncontroverted. The court found the claim valid and awarded the sum claimed, general damages for breach of contract, and interest. The defendant's counterclaim was dismissed for want of prosecution. The court exercised discretion to reduce the proposed general damages from Shs. 5 million to Shs. 3 million, considering the circumstances. Interest was awarded at 20% per annum on the liquidated sum and at court rate on general damages. Costs were also awarded to the plaintiff.
Obiter and limits
- Adjournment by letter is not allowed by Ugandan courts; counsel should have arranged for another advocate to hold brief if indisposed.
- The repeated failure of the defendant and counsel to appear justified proceeding ex parte and dismissing the counterclaim.
Court disposition
judgment_for_plaintiff
- The defendant shall pay the plaintiff Shs. 35,057,429.
- Interest on the above sum at 20% per annum from date of filing until payment in full.
- The defendant shall pay the plaintiff Shs. 3,000,000 as general damages.
- Interest on general damages at court rate from date of judgment until payment in full.
- The defendant shall pay the costs of the suit.
Source and reliance status
High Court of Uganda
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
High Court of Uganda
Judgment
{\rtf1\ansi\ansicpg1252\uc1\deff0\stshfdbch0\stshfloch0\stshfhich0\stshfbi0\deflang2057\deflangfe2057{\fonttbl{\f0\froman\fcharset0\fprq2{\*\panose 02020603050405020304}Times New Roman;}{\f148\froman\fcharset238\fprq2 Times New Roman CE;} {\f149\froman\fcharset204\fprq2 Times New Roman Cyr;}{\f151\froman\fcharset161\fprq2 Times New Roman Greek;}{\f152\froman\fcharset162\fprq2 Times New Roman Tur;}{\f153\froman\fcharset177\fprq2 Times New Roman (Hebrew);} {\f154\froman\fcharset178\fprq2 Times New Roman (Arabic);}{\f155\froman\fcharset186\fprq2 Times New Roman Baltic;}{\f156\froman\fcharset163\fprq2 Times New Roman (Vietnamese);}}{\colortbl;\red0\green0\blue0;\red0\green0\blue255;\red0\green255\blue255; \red0\green255\blue0;\red255\green0\blue255;\red255\green0\blue0;\red255\green255\blue0;\red255\green255\blue255;\red0\green0\blue128;\red0\green128\blue128;\red0\green128\blue0;\red128\green0\blue128;\red128\green0\blue0;\red128\green128\blue0; \red128\green128\blue128;\red192\green192\blue192;}{\stylesheet{\ql \li0\ri0\widctlpar\aspalpha\aspnum\faauto\adjustright\rin0\lin0\itap0 \fs24\lang2057\langfe2057\cgrid\langnp2057\langfenp2057 \snext0 Normal;}{\*\cs10 \additive \ssemihidden Default Paragraph
Font;}{\*\ts11\tsrowd\trftsWidthB3\trpaddl108\trpaddr108\trpaddfl3\trpaddft3\trpaddfb3\trpaddfr3\trcbpat1\trcfpat1\tscellwidthfts0\tsvertalt\tsbrdrt\tsbrdrl\tsbrdrb\tsbrdrr\tsbrdrdgl\tsbrdrdgr\tsbrdrh\tsbrdrv \ql \li0\ri0\widctlpar\aspalpha\aspnum\faauto\adjustright\rin0\lin0\itap0 \fs20\lang1024\langfe1024\cgrid\langnp1024\langfenp1024 \snext11 \ssemihidden Normal Table;}{ \s15\ql \li0\ri0\sb100\sa100\sbauto1\saauto1\widctlpar\aspalpha\aspnum\faauto\adjustright\rin0\lin0\itap0 \fs24\lang2057\langfe2057\cgrid\langnp2057\langfenp2057 \sbasedon0 \snext15 \styrsid4218726 Normal (Web);}} {\*\latentstyles\lsdstimax156\lsdlockeddef0}{\*\pgptbl {\pgp\ipgp0\itap0\li0\ri0\sb0\sa0}}{\*\rsidtbl \rsid4133107\rsid4218726\rsid8402778\rsid9502911\rsid12460644}{\*\generator Microsoft Word 11.0.5604;}{\info{\title THE REPUBLIC OF UGANDA } {\author Administrator}{\operator jchemeri}{\creatim\yr2009\mo6\dy12\hr3\min3}{\revtim\yr2009\mo6\dy12\hr3\min3}{\version2}{\edmins18}{\nofpages5}{\nofwords1162}{\nofchars6625}{\*\company
JSI}{\nofcharsws7772}{\vern24689}}\paperw11906\paperh16838 \widowctrl\ftnbj\aenddoc\noxlattoyen\expshrtn\noultrlspc\dntblnsbdb\nospaceforul\formshade\horzdoc\dgmargin\dghspace180\dgvspace180\dghorigin1800\dgvorigin1440\dghshow1\dgvshow1 \jexpand\viewkind1\viewscale100\pgbrdrhead\pgbrdrfoot\splytwnine\ftnlytwnine\htmautsp\nolnhtadjtbl\useltbaln\alntblind\lytcalctblwd\lyttblrtgr\lnbrkrule\nobrkwrptbl\snaptogridincell\allowfieldendsel\wrppunct \asianbrkrule\rsidroot4218726\newtblstyruls\nogrowautofit \fet0\sectd \linex0\headery708\footery708\colsx708\endnhere\sectlinegrid360\sectdefaultcl\sectrsid4133107\sftnbj {\*\pnseclvl1\pnucrm\pnstart1\pnindent720\pnhang {\pntxta .}}{\*\pnseclvl2 \pnucltr\pnstart1\pnindent720\pnhang {\pntxta .}}{\*\pnseclvl3\pndec\pnstart1\pnindent720\pnhang {\pntxta .}}{\*\pnseclvl4\pnlcltr\pnstart1\pnindent720\pnhang {\pntxta )}}{\*\pnseclvl5\pndec\pnstart1\pnindent720\pnhang {\pntxtb (}{\pntxta )}}{\*\pnseclvl6 \pnlcltr\pnstart1\pnindent720\pnhang {\pntxtb (}{\pntxta )}}{\*\pnseclvl7\pnlcrm\pnstart1\pnindent720\pnhang {\pntxtb (}{\pntxta )}}{\*\pnseclvl8\pnlcltr\pnstart1\pnindent720\pnhang {\pntxtb (}{\pntxta )}}{\*\pnseclvl9\pnlcrm\pnstart1\pnindent720\pnhang {\pntxtb (}{\pntxta )}}\pard\plain \s15\ql \li0\ri0\sb100\sa240\sbauto1\sl360\slmult1\widctlpar\aspalpha\aspnum\faauto\adjustright\rin0\lin0\itap0\ipgp1\pararsid8402778
\fs24\lang2057\langfe2057\cgrid\langnp2057\langfenp2057 { \b\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 }{\b\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 THE REPUBLIC OF UGANDA \line IN THE HIGH COURT OF UGANDA AT KAMPALA}{ \b\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 \line (Commercial Cour}{\b\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 t) \line }{ \b\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 }{\b\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 HCCS NO. 696 OF 2002 \line PETRO (U) LTD ::::::::::::::::::::::::::::::::::::: PLAINTIFF \line }{ \b\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 }{\b\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 VERSUS \line SAILESH KUMAR MAMBHAI PATEL ::::::::::::::: DEFENDANT \line BEFORE: }{ \b\ul\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 THE HON. LADY JUSTICE M. S. ARACH }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \emdash }{\b\ul\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 AMOKO}{ \b\ul\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 \par }{\b\ul\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 }{\b\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778
}{\b\ul\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 }{ \b\ul\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 JUDGMENT: }{\b\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \line }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 The Plaintiff is a limited liability company dealing in Petroleum products at the material time. The Defendant is a businessman. The Plaintiff brought this suit to recover the sum of Shs.35}{\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 , 057,429}{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 -, being payment for petroleum products supplied to the Defendant in May 2002. The Plaintiff also}{\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 prayed for interest and costs. \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 The Defendant filed a written statement of Defence denying liability and counter claimed a total of Shs.69}{\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 , 346,846}{ \lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 - as a result of various dealings between them itemized there under.}{\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 Efforts to settle the matter amicably failed inspite of an
assurance by Defence counsel Mr. Dhagira on the 9/3/2004 that his client had instructed him to seek an adjournment of the case for at least one month with a view to an amicable settlement. On that day, I gave the parties a time table to follow in a bid to exploring a settlement; and adjourned the case to 9/3/2004 to receive a report from the parties.}{ \lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 On 24/6/2004, however, neither Mr. Dhagira nor his client was represented in Court. Mr. Dhagira had written a letter dated 22/6/2004, to the Plaintiff\rquote s counsel and copied the same to the Registrar of this Court applying for adjournment to another date, on the ground that he was \'93indisposed,\'94 whatever that meant, and that his client was in London for medical treatment. No proposals had been exchanged by that date as directed by Court. Mr. Kandeebe learned counsel for the Plaintiff pointed out, rightly, that the matter had been adjourned several times on the instance of Mr. Dhagira and his client and that adjournment by letter is not allowed by our Courts.}{\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \line I accepted the reasons given and ruled that the Defence counsel should have had at least the
professional courtesy of requesting another advocate of this Court to ho ld brief for him, as the practice is, if he was indeed indisposed as alleged, instead of merely applying for adjournment by letter. I denied the request for adjournment and allowed the matter to proceed exparte under 09}{ \lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 rule 17 (1) (a) of the CPR. }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \par At t he commencement of the hearing, Mr. Kandeebe applied for dismissal of the counterclaim under 09 rule 19 CPR, with costs due to the absence of the Defendant who was the Plaintiff by counterclaim. I granted the application and dismissed the counterclaim wit h costs under Order 9 rule 19 CPR which provides in the relevant part that:}{\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 \par }{\i\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \'9319. Where a Defendant appears, and the Plaintiff does not appear, when the suit is called on for hearing, the Court shall make an order that the suit be dismissed, unless the Defe ndant admits the claim remainder.\'94}{\i\lang1033\langfe2057\langnp1033\insrsid12460644\charrsid8402778 \par }{\i\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 The Plaintiff who was the Defendant in the
counterclaim had filed a reply denying the counterclaim in toto and praying for its dismissal.}{\lang1033\langfe2057\langnp1033\insrsid9502911\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 The following issues were framed for determination: \line 1. Whether the money claimed is due and outstanding. \line 2. Remedies.}{ \lang1033\langfe2057\langnp1033\insrsid9502911\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 The Plaintiff called one witness, Mr. Ahmed Ladha. He told Court that he is the current General Manager of the Plaintiff. The Defendant was a dealer in petroleum products from the company as well as a landlord of the Plaintiff\rquote s Mbale Petrol Station. They signed a dealership agreement in the year 2000. (Exhibit P1). In 2002 the Plaintiff supplied the Defendant with fuel on th}{\lang1033\langfe2057\langnp1033\insrsid9502911\charrsid8402778 e understanding that he would \line }{ \lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 send the money. The Defendant instead sent a fax to the Plai ntiff asking the Plaintiff to take over the station because he was unable to run it due to poor health. Both parties made hand over reports (Exhibit P4) before the Plaintiff took over the petrol station. At that time, the Plaintiff took over three product s valued at
Shs.2}{\lang1033\langfe2057\langnp1033\insrsid9502911\charrsid8402778 , 557,571}{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 - (Exhibit P3) the products were: \line - PMS (Petrol) \emdash 420.8 litres. \line - Diesel \emdash 1,411.8 litres. \line - BIK (Kerosene) \emdash 260.7 litres.}{\lang1033\langfe2057\langnp1033\insrsid9502911\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 The value was recorded in a debit note No. 340 (Exhibit P3). \line The Shs.35}{\lang1033\langfe2057\langnp1033\insrsid9502911\charrsid8402778 , 057,429}{ \lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 - claimed is a result of two unpaid invoices namely: \line 1. PUG 11048 supplied on 23/5/2002 for Shs. 19,405,000-. \line 2. PUG 11152 dated 30/5/2002 for Shs. 18,210,000- received on 31/5/2002. \line Less Shs.2}{\lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 , 557,571}{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 - on the credit note.}{ \lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 The deliveries were received by the Defendants Manag er, called Apollo also known as Paulo. The tax invoices/delivery notes bear the stamp of the Defendant Company and the seal at the back because the trucks were always sealed with the
seal number. The invoices are stamped with URA stamp proving that the Go vernment has collected duty. The total form the two invoices is Shs.37,057,429- including the Shs.2,557,571- on the credit note. They did not owe the Defendant any money.}{\lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 The Plaintiff has demanded for this payment several times and the Defendant has fa iled to pay on the ground that he is sick, he is dying and he is alone. The Court should order him to pay this money plus interest and general damages because it has been outstanding for the last two years. He should also pay the costs.}{ \lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 Mr. Kandeebe made brief submissions and prayed the Court to enter Judgment in favour of his client as prayed. I have considered the case before me and the evidence adduced by the Plaintiff in support of its claim. I must say, I agree with Mr. Kandeehe that the Plaintiff ha s proved its claim to the required standard, in the absence of any controverting evidence. The Plaintiff has tendered exhibits P1 \emdash 4 showing the dealership agreement between them (Exhibit P1). The two delivery notes/tax invoices No. PUG \emdash 11152 dated 30/5/2002 and No. PUG \emdash
11048 dated 23/5/2002 showing delivery of petroleum products to the Defendant station. The invoices bear the Defendants stamp and a signatures of the Defendant\rquote s official. (Exhibit P2 (i) and (ii)). The exhibits are consistent with the oral testimony of the Plaintiff\rquote s General Manager. The answer to the first issue is therefore in the affirmative.}{ \lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \line Regarding the second issue, I also accept Mr. Kandeebe\rquote s submission that the \line Plaintiff be awarded general damages for breach of contract. The testimony of Mr. \line Ladha is clear on this. He told Court that his company supplied the Defendant with \line petroleum products against taxed invoices. The Defendant does not deny receiving \line the said products. According to Mr. Ladha, when he demanded for paym ent, the Defendant refused to pay, and instead told them to go and take over the petrol station. That he has made several demands to the Defendant but he failed to pay. This is definitely in breach of the dealership agreement and highly inconveniencing to the Plaintiff. Mr. Kandeebe has proposed Shs.5m as appropriate quantum. I think this is high. I reduce it to Shs.3m, taking the circumstances of this case into
account.}{\lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 Mr. Kandeebe prayed for interest at 28% p.a on the liquidated sum; and at Court rate o n the general damages. I accept his submission and award interest at 20% p.a on the liquidated sum and at Court rate on the general damages.}{\lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 In the result, Judgment is hereby entered in favour of the Plaintiff as follows: \line 1. Shs.35}{\lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 , 057,429}{ \lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 -. \line 2. Interest on (1) at 20% p.a from date of filing till payment in full. \line 3. Shs.3m, general damages. \line 4. Interest on (3) at Court rate from date of Judgment till payment in full. \line 5. Costs of the suit.}{\lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 \par }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 M. S. Arach \emdash Amoko \line }{\b\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 JUDGE \line }{\lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 28/6/20 04 \line }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \par
}{\ul\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 Judgment delivered in Court in the presence of: }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \line 1. Mr. Kwarisima Wilson holding brief for Mr. Kandeebe for the Plaintiff. \line 2. Mr. Okuni \emdash Court clerk. \line Absent - Defendant and counsel. \line NB: Matter was course listed for this afternoon at 2.30 p.m. \line M. S. Arach \emdash Amoko \line }{\b\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 JUDGE \line }{\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 28/}{\lang1033\langfe2057\langnp1033\insrsid8402778\charrsid8402778 6/2004 \line }{ \lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \par }\pard\plain \ql \li0\ri0\sl360\slmult1\widctlpar\aspalpha\aspnum\faauto\adjustright\rin0\lin0\itap0\pararsid8402778 \fs24\lang2057\langfe2057\cgrid\langnp2057\langfenp2057 {\lang1033\langfe2057\langnp1033\insrsid4218726\charrsid8402778 \par }}