Lal v East African Builders Merchants (Civil Appeal No. 53 of 1950) [1951] EACA 50 (1 January 1951)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The Court of Appeal held that there was no error of law apparent on the face of the arbitral award. The arbitrators did not state any legal proposition, nor did they misapply any legal principle in the award. The findings were factual, and the award did not expressly state that the contract was an entire one for a lump sum, nor did it state that the appellant was entitled to payment contrary to law. The court emphasized that an error of law must be apparent from the award itself or a document incorporated into it, not inferred by the judge from the facts or silence of the arbitrators. The learned judge in the court below was wrong to infer a legal error where none was stated. Accordingly, the appeal was allowed, and the order remitting the award was set aside.

Court disposition

appeal allowed

Orders

  • The appeal is allowed with costs, including costs of the cross appeal and the motion to remit or set aside the award in the court below.
  • The case is remitted back to the Supreme Court of Kenya for judgment in accordance with Order XLV Rule 16.

02

Material facts

Parties

Sohan Lal

Appellant Counsel: D. N. Khanna

East African Builders Merchants

Respondent Counsel: Bhandari

Amounts and remedies

  • Sum Awarded to Sohan Lal for Work Executed Before Termination (less Already Received): KES 14,555
  • Set Off in Favour of East African Builders Merchants for Defective Work: KES 4,354
  • Costs of Reference and Award (to Be Borne Equally): KES 1,800

03

Procedural history

  1. Posture

    Civil Appeal / Appeal From Order Remitting Arbitral Award for Reconsideration

04

Questions and positions

Legal issues

Party arguments

Applicant
Counsel for the appellant argued that there was no error of law apparent on the face of the award. The arbitrators did not state any legal proposition, nor did they misapply any legal principle. Even if the contract was for a lump sum, the award does not expressly state that the appellant was entitled to payment contrary to law. The findings were factual, and the court should not infer a legal error where none is stated.
Respondent
Counsel for the respondent contended that the arbitrators' findings, particularly the recitals and the award of payment despite defective performance, amounted to an error of law on the face of the award. He argued that the contract was entire for a lump sum, and under the law, no payment should be made if the contract was not completed. He relied on authorities suggesting that such an inference is permissible.

05

Court’s reasoning

  1. 01

    Champsey Bhara & Co., Ltd. v. Jivraj Baloo Spinning and Weaving Co., Ltd., L. R. 50 I. A. 324

    An error of law on the face of the award must be found in the award or a document incorporated into it, stating a legal proposition that is erroneous.

  2. 02

    Unreported Civil Appeals 27 of 1949 and 36 of 1950 (East African Court of Appeal)

    If a contract is entire and for a lump sum, a contractor who fails to complete the works is not entitled to recover anything.

  3. 03

    Saleh Mohamed v. Nathoomal Kessamal, L. R. 54 I. A. 427

    Courts should not infer a legal error from silence or absence of a legal proposition in an arbitral award.

06

Ratio, limits and disposition

Ratio decidendi

The Court of Appeal held that there was no error of law apparent on the face of the arbitral award. The arbitrators did not state any legal proposition, nor did they misapply any legal principle in the award. The findings were factual, and the award did not expressly state that the contract was an entire one for a lump sum, nor did it state that the appellant was entitled to payment contrary to law. The court emphasized that an error of law must be apparent from the award itself or a document incorporated into it, not inferred by the judge from the facts or silence of the arbitrators. The learned judge in the court below was wrong to infer a legal error where none was stated. Accordingly, the appeal was allowed, and the order remitting the award was set aside.

Obiter and limits

  • Parties who refer disputes to arbitration are ordinarily bound by mistakes of law or fact made by the arbitrators.
  • The regret expressed by some judges regarding the rule allowing remittal of awards for errors of law on the face of the award is noted, but the rule is prescribed by statute in this jurisdiction.
  • Authorities cited by the respondent do not support the proposition that a legal error can be inferred from silence or absence of a legal proposition in the award.

Court disposition

appeal allowed

  • The appeal is allowed with costs, including costs of the cross appeal and the motion to remit or set aside the award in the court below.
  • The case is remitted back to the Supreme Court of Kenya for judgment in accordance with Order XLV Rule 16.

Source and reliance status

East African Court of Appeal

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Source document

Judgment reading view

Judgment text

The complete available source text.

Source document

East African Court of Appeal

Judgment

[1951] EACA 50

COURT OF APPEAL FOR EASTERN AFRICA

Before SIR BARCLAY NIHILL (President), LOCKHART-SMITH (Ag. Vice-President), and BOURKE, Ag. C. J. (Kenya)

SOHAN LAL, Appellant (Original Plaintiff)

ν.

EAST AFRICAN BUILDERS MERCHANTS, Respondents (Original Defendants)

Civil Appeal No. 53 of 1950

(Appeal from the decision of H. M. Supreme Court of Kenya—De Lestang, J.)

Arbitrator's award—Apparent illegality upon the face of—Power of Court to look behind terms of the award and make findings of fact.

The respondents applied to the Supreme Court for an order remitting back their award to the arbitrators for reconsideration. The Court found that an objection to the legality of the award was apparent upon the face of it inasmuch as the arbitrators, having found that the termination of the contract beween the parties was due to slow progress and defective workmanship on the part of the appellant, erred in law in awarding him anything for work done prior to the termination of the contract which was for a lump sum. The application to remit was granted.

iHeld (22-6-51).—That the arbitrators had not stated in their award that the contract was for a lump sum. The Judge was wrong in saying "I infer from these findings (of the arbitrators) that there was here an entire and in was therefore no apparent illegality upon the face of the award and the appeal succeeded.

Cases referred to: Champsey Bhara & Co., Ltd. v. Jivraj Baloo Spinning and Weaving Co., Ltd., L. R. 50 I. A. 324; Saleh Mohamed v. Nathoomal Kessamal, L. R. 54 I. A. 427.

D. N. Khanna for the appellant. $\mathcal{D}$

Bhandari for the respondents.

$\mathcal{L}^{\text{max}}$

JUDGMENT (delivered by LOCKHART-SMITH, Ag. Vice-President).—This is an appeal, with the leave of the Supreme Court of Kenya, against an Order made by de Lestang, J. in Kenya Civil Case No. 643 of 1949.

In the course of that suit, an award was filed by Arbitrators appointed under an order of reference made therein, and the defendants moved the Court under Order 45 Rules 14 and 15 of the Civil Procedure (Revised) Rules, 1948, to set aside the award or to remit it to the Arbitrators for reconsideration.

On the 28th of August, 1950, de Lestang, J. made an Order deciding that the application to set aside the award was barred by limitation, but directed that the application for remitting back the award should proceed. He reserved the costs of the application.

On the 27th of September, 1950, the learned Judge ruled that an objection to the legality of the award was apparent upon the face of it (which is one of the grounds under Rule 14 enabling the Court to remit an award—see paragraph $(c)$ that the award must, therefore, be remitted to the Arbitrators, and that as each party had succeeded on one issue each party would bear his own costs of the application to set aside or remit the award.

An order was drawn up accordingly, and from that order the appellant (the original plaintiff) now appeals.

Mr. Khanna for the appellant, contends that there is no objection to the legality of the award apparent upon the face of it. He has referred us to a number of authorities the effect of which is, in my opinion, adequately summarized for the purposes of this appeal, in the following passage from the judgment of their Lordships of the Judicial Committee of the Privy Council in Champsey Bhara and Co. Ltd. v. Jivraj Baloo Spinning and Weaving Co. Ltd., L. R. 50 I. A. 324 (followed by their Lordships in Saleh Mohamed v. Nathoomal Kessamal, L. R. 54 I. A. 427:

"An error in law on the face of the award means, in their Lordships view, that you find in the award or a document actually incorporated thereto, as for instance a note appended by the arbitrator stating the reasons for his judgment, some legal proposition which is the basis of the award and which you can say is erroneous."

The Award reads as follows: $-$

"WHEREAS East African Builders Merchants by an agreement in writing made between the Mowlem Construction Company Limited on the one part Builders Merchants the other African $\overline{on}$ part $and$ East undertook the supply of labour for the execution and completion of a certain block of Buildings known as Standard Bank Flats Nairobi within the terms of the contract Agreement in force between The Standard Bank of South Africa Limited on the one part and the Mowlem Construction Company Limited on the other.

AND WHEREAS Sohan Lal by an agreement in writing dated the 14th April, 1949, made between East African Builders Merchants on the one part and Sohan Lal on the other part undertook the supply of labour for the execution and completion of certain carpenters' and Joiners' work at<br>Standard Bank Flats for the sum of Shillings Thirty Thousand (Sh. 30,000/-), the work to be completed by 1st June, 1949, within the terms of the sub-Contract entered into by The Mowlem Construction Company, Ltd., and East African Builders Merchants.

AND WHEREAS a difference has arisen between Sohan Lal and East African Builders Merchants as to the amount of money due to the said Sohan Lal from East African Builders Merchants.

AND WHEREAS the said difference has by order of His Majesty's Supreme Court of Kenya dated 28th March, 1949, been referred to us Frederick Charles Bridle and Ghulam Rasool the Arbitrators appointed by the said Order.

Now We the said Frederick Charles Bridle and Ghulam Rasool having taken upon ourselves the burden of the said Reference and having heard both parties and having inspected the drawings and documents produced to us by the parties and having obtained all other information we require do make and publish our Award as follows: -

- 1. We find that the termination of the Sub-Contract by the Mowlem Construction Company Limited was due to slow progress and defective workmanship on the part of Sohan Lal. - 2. We award that Sohan Lal is entitled to recover from East African Builders Merchants for work executed before the termination of the Sub-Contract the sum of

| Less already received on account: | | | Sh. $12.555/00/-$<br>Sh. $1,000/00/-$ | |-----------------------------------|--|--|---------------------------------------| | | | | Sh. $14.555/00/-$ |

- 3. We award that East African Builders Merchants are entitled to recover from Sohan Lal and to set off the amount against the sum of Sh. $11,555/-$ the sum of Sh. 4,354/- in respect of the pulling down and re-execution of certain work of a defective nature done by Sohan Lal. - 4. We award as regards the Costs of the Action that each side pay their own. - 5. We award as regards the Costs of this Reference and Award amounting to Sh. 1,800/- that this be borne by both parties in equal proportions.

AS WITNESS OUR HANDS THIS TWENTY-NINTH DAY OF JUNE ONE THOUSAND NINE HUNDRED AND FIFTY.

> (Signed) F. C. BRIDLE, (Signed) G. RASOOL, Joint Arbitrators."

> > 冇

Where is the erroneous legal proposition in this Award? Mr. Khanna submits that there is none. It is not disputed that if a contract is an entire one to be completed for a lump sum, the party who is liable to complete the contract works is not entitled to recover anything if he fails to do so. This Court has so held in Civil Appeals 27 of 1949 and 36 of 1950. (Not yet reported.)

But the Arbitrators have nowhere stated this principle and then wrongly applied it. Nor have they erroneously stated any proposition of law.

Even if, as Mr. Bhandari, for the respondent, submits, the second recital of the Award amounts to a finding of fact, I agree with Mr. Khanna that it does not necessarily amount to a finding that the contract was an entire one for a lump sum. The plaint avers that instalments were to be paid for work actually done; the recital itself states that the agreement was to be completed within the terms of the Sub-Contract "which are not stated: and generally the recital is equally consistent with an unexpressed view of the facts and the law on the part of the Arbitrators differing from that contended for by Mr. Bhandari and by which the parties would be bound.

I would go further, however, and say that even if the second recital does amount to a finding of fact by the Arbitrators that the contract was an entire one for a lump sum, and even if the finding in paragraph 1 of the Award amounts to a finding that the contract works were never completed (which it does not expressly say) it is still impossible to find in the Award some legal proposition which is the basis of it "and which you can say is erroneous."

If the Arbitrators had referred to the decisions in Civil Appeals Nos. 27 of 1949 and 36 of 1950, and had then declined to follow them, or if they had said some such thing as "the law is that a contractor who fails to complete an entire contract for a lump sum is nevertheless entitled to payment for so much of the work as is actually done on a quantum meruit basis", then I would agree that there was an objection to the legality of the Award apparent upon the face of it, but in the case of the present Award I find it impossible to reach any such conclusion.

The learned Judge was constrained to *infer* the facts upon which he based his Ruling from what he regarded as the finding which the Arbitrators had made, and he had to apply his own knowledge of the law to the facts before he could say that in law the appellant was not entitled to recover anything from the respondents. He could not rely on any misstatement of the law in the Award itself, because there was none.

When the parties to a dispute refer it for decision to Arbitrators of their own choice and agree to be bound by their decision, they must, ordinarily speaking, be held to be bound by any mistakes of law or fact made by the Arbitrators, and in England many learned Judges have shared the regret expressed by Williams, J. in Hodgkinson and Fernie, 3 C. B. (New Series) 189, that it should ever have become well-settled that an award might be remitted to the arbitrators on account of an error of law apparent upon the face of it. In England, of course, the rule stems from the Common Law and is not, as in India and in this Colony, prescribed by statute.

Mr. Bhandari has referred us to a number of authorities which seem to me to be uniformly against him.

First of all he cites Champsey Bhara's case supra, and suggests that there is an "irresistible inference" that the Abitrators made an error of law on the face of the record in the sense of the passage from their Lordships' judgment which<br>I have quoted above. The plain dictionary meaning of the word "proposition" in<br>this context is, "the act of stating anything; that which is sta and how one can infer that a statement was made which was never made in fact is beyond my understanding. One may perhaps infer from the Award that the Arbitrators did not know what the law was, or that, if they had attempted to state it, they would have stated it wrongly, but that is very far from the same thing as finding in the Award a legal proposition "which you can say is erroneous".

Mr. Bhandari next referred to Meenakshi Mills Ltd. v. Langely & Co. I. L. R. 58 Bombay 288. That was a case where the award was, as Beaumont, C. J., said (at page 294) "based on the construction of by-law No. 74", which by-law the arbitrators had cited in their award and had then wrongly construed. The decision has no possible bearing on the present case.

Mr. Bhandari further referred to-

- (a) a passage in Chitale's Code of Civil Procedure which merely paraphrases the passage from *Chamsey Bhara's* case quoted above. - (b) Sreelal Mangtulal v. Madan, I. L. R. 52 Calcutta 100, in which the Arbitrator's award was "more like a judgment of a Judge, which is subject to appeal, than the award of an arbitrator" (per Sanderson, C. J. at page 110), and in which the arbitrator, having framed issues heard counsel and noted authorities, made a finding "upon the authorities discussed" which the authorities did not support, - (c) a case mentioned at page 160 of the 10th Edition of Russel on Arbitration in which an award was remitted because the arbitrator had exceeded his terms of reference. None of these authorities in my opinion, have any relevance to the present case, or assist Mr. Bhandari in the slightest.

I would allow the appeal.

SIR BARCLAY NIHILL (President).—I concur in the judgment just delivered by the learned Justice of Appeal—this appeal is allowed with costs, which shall include the costs of the cross appeal and the costs of the motion to remit or set aside the award filed in the Court below. And in view of the judgment of this court about to be delivered in the considered appeal 43 of 1950 we direct that this case be remitted back to the Supreme Court of Kenya for judgment in accordance with the provision of Order XLV R.

16.

BOURKE, Ag. C. J. (Kenya).—I agree.

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Champsey Bhara & Co., Ltd. v. Jivraj Baloo Spinning and Weaving Co., Ltd., L. R. 50 I. A. 324

Case cited

Saleh Mohamed v. Nathoomal Kessamal, L. R. 54 I. A. 427

Case cited

Meenakshi Mills Ltd. v. Langely & Co. I. L. R. 58 Bombay 288

Case cited

Sreelal Mangtulal v. Madan, I. L. R. 52 Calcutta 100

Case cited

Hodgkinson and Fernie, 3 C. B. (New Series) 189

Case cited

Order 45 Rules 14 and 15 of the Civil Procedure (Revised) Rules, 1948 (Kenya)

Legislation

Legislation referenced in the available case record.

Order XLV Rule 16 of the Civil Procedure (Revised) Rules, 1948 (Kenya)

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this JurisAssist collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.