01

Holding and result

The court found that the dispute regarding the Ushs.35,000,000/= debt had been conclusively settled by the deed of settlement dated 14th November 1999, which expressly provided that all claims and obligations between the parties were extinguished. The court held that the plaintiff was estopped from denying the efficacy of the settlement agreement and from pursuing further litigation on the same claim. The court emphasized that settlements reached through alternative dispute resolution mechanisms and reduced to writing must be recognized and enforced, in accordance with Article 126(2)(e) of the Constitution and Section 33 of the Judicature Act. As such, the court dismissed the suit without considering the remaining issues, enforcing the settlement and awarding costs to the defendant.

Court disposition

suit dismissed with costs to the defendant

Orders

  • The suit is dismissed.
  • The plaintiff shall pay costs to the defendant.

02

Material facts

Parties

Bhasker Kotecha

Plaintiff Counsel: M. Ssegawa

Adam Mohamed

Defendant Counsel: M. Bakidde

Idow Ali Idow

Third Party Counsel: Bamwite

Adam Abubaker

Third Party Counsel: Bamwite

Khalif Abubaker

Third Party Counsel: Bamwite

Amounts and remedies

  • Claimed Debt: UGX 35,000,000

03

Procedural history

  1. Posture

    Civil Suit / Judgment

04

Questions and positions

Legal issues

Party arguments

Applicant
Counsel for the plaintiff argued that the defendant and third parties' indebtedness is evidenced by a guarantee agreement dated 26th March 1995, acknowledging a balance of Ushs.35,000,000/=. The defendant, as guarantor, issued a cheque for this amount, which was dishonoured. The plaintiff dismissed claims of duress in signing the agreement, noting that no challenge was made for 12 years. The plaintiff contended the debt remains outstanding and payable.
Respondent
Counsel for the defendant argued that the guarantee agreement was superseded by a deed of settlement dated 14th November 1999, which provided that all claims and obligations between the parties were extinguished. The settlement included the Ushs.35,000,000/= in dispute. The defendant submitted that the plaintiff is estopped from pursuing the claim, relying on the principle that parties are bound by the language of a deed.

05

Court’s reasoning

  1. 01

    Deed of Settlement dated 14th November 1999; Bateman v Hunt [1904] 2 K.B. 530

    A settlement agreement between parties, once executed, extinguishes prior claims and bars further litigation on the same subject matter.

  2. 02

    Muhammad Muhammad Al Hassan v Ibrahim Al Gasim HCCS 504 of 2005 (unreported); Buildtrust Construction Ltd v Maitha Rugasira HCCS No. 288 of 2005 (unreported)

    Courts are bound to recognize and enforce settlements as a form of alternative dispute resolution under Article 126(2)(e) of the Constitution of Uganda 1995.

  3. 03

    Section 33, Judicature Act

    Section 33 of the Judicature Act requires courts to avoid multiplicity of proceedings and enforce settlements where appropriate.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the dispute regarding the Ushs.35,000,000/= debt had been conclusively settled by the deed of settlement dated 14th November 1999, which expressly provided that all claims and obligations between the parties were extinguished. The court held that the plaintiff was estopped from denying the efficacy of the settlement agreement and from pursuing further litigation on the same claim. The court emphasized that settlements reached through alternative dispute resolution mechanisms and reduced to writing must be recognized and enforced, in accordance with Article 126(2)(e) of the Constitution and Section 33 of the Judicature Act. As such, the court dismissed the suit without considering the remaining issues, enforcing the settlement and awarding costs to the defendant.

Obiter and limits

  • Criminal cases are not as easily withdrawn as civil cases, and the outcome of the criminal proceedings does not affect the validity of the civil settlement.
  • The court is bound to avoid a multiplicity of cases and to enforce settlements that bring litigation to an end.

Court disposition

suit dismissed with costs to the defendant

  • The suit is dismissed.
  • The plaintiff shall pay costs to the defendant.

Source and reliance status

Commercial Court of Uganda

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Source document

Judgment reading view

Judgment text

The complete available source text.

Source document

Commercial Court of Uganda

Judgment

[2008] UGCommC 88

THE REPUBLIC OF UGANDA

IN THE HIGH COURT OF UGANDA AT KAMPALA (COMMERCIAL COURT DIVISION)

HCT - 00 - CC - CA - 674 - 2000

BHASKER KOTECHA ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: PLAINTIFF

VERSUS

ADAM MOHAMED ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: DEFENDANT

AND

1. IDOW ALI IDOW 2. ADAM ABUBAKER :::::::::::::::::::::::::::::::::::::::::: THIRD PARTIES 3. KHALIF ABUBAKER

BEFORE: THE HON. JUSTICE GEOFFREY KIRYABWIRE.

J U D G M E N T:

This suit was brought by the Plaintiff against the Defendant for the recovery of the sum of Ushs.35,000,000/= being the value of a dishonoured cheque dated 28th October, 1998.

The history of this case is long and begins some time in 1994. At that time the third parties to this action then trading as M/S Kadi Abdi & Brothers are alleged to have accumulated a debt with the Plaintiff of about Ushs.50,000,000/=. This debt became a source of conflict between the parties as well as threatened legal action. However, on or about the 26th March 1995 the parties entered into an agreement of guarantee

where by partial settlement of the debt was made leaving an unpaid balance of Ushs.35,000,000/= which was to be paid in installments.

This agreement was between the Plaintiff and the third parties and the Defendant was named as guarantor. It is for this reason that the Defendant took out a third party notice against the third parties for indemnity.

The outstanding amount of Ushs.35,000,000/= remains unpaid as a cheque issued for the said amount when presented at the bank was returned unpaid.

The parties agreed to the following issues for trial.

- 1. Whether there was indebtness between the Defendant, third parties owing to the Plaintiff. - 2. If there was indebtness, whether it was satisfied or discharged. - 3. Whether the said indebtness was guaranteed. - 4. Remedies.

Mr. M. Ssegawa appeared for the Plaintiff, Mr. M. Bakidde appeared for the Defendant and Mr. Bamwite appeared for the third parties.

Issues No. 1: Whether there was indebtness between the Defendants, third party owing to the Plaintiff?

Counsel for the Plaintiff submitted that the indebtness of the Defendant and the third parties is evidenced by an agreement of guarantee (Exh. P.3) dated 26th March 1995. By the said agreement the third parties acknowledged liability of Ushs.50,000,000/= which was reduced by Ushs.15,000,000/= leaving a balance of Ushs.35,000,000/=. He submitted that the third parties allege that the balance was paid but offered no evidence in that regard. The evidence that does exist is that the Defendant as guarantor issued a cheque (Exh. P.1) which when banked was returned unpaid (Exh. P.2).

Counsel for the Plaintiff dismissed the Defendant and third parties allegations that the agreement of guarantee was signed under duress at a police station where the third parties were detained. He submitted that if there was any illegitimate pressure applied on the third parties then it was approbated when the pressure ceased to operate on them. This is because the third parties and the Defendants in 12 years have done nothing to challenge the said agreement. In this regard I was referred to the decision of Universe Tankships Inc of Monrovia V International Transport Works Federation [1983] 1 AC 366.

He submitted therefore that the debt of Ushs.35,000,000/= was still outstanding and payable.

Counsel for the Defendant on the other hand submitted that the agreement of guarantee was over taken by a deed of settlement (Exh. P.5) dated 14th November 1999. He submitted that paragraph 3 of that settlement provided

"…That on the execution of this Agreement, the parties shall have no claim or any obligations that can be enforced in any court of law against or upon the other…".

Counsel for the Defendant submitted that among the disputes that were settled according to paragraph 1 of the settlement dated 14th November 1999 was the "…Shs.35 million of the pending case…" Counsel for the Defendant submitted that the pending case referred to there at there time was HCCS No. 133 of 1999

Bhasker Kotecha V Adam Mohammed

which was dismissed. High Court Civil Suit No. 133 of 1999, counsel for the Defendant submitted was the predecessor to this very suit which still has the same parties.

He submitted that by the said settlement both parties put aside any litigation and the parties should be made to be bound by that agreement and estopped from pursuing the claim. In this regard I was referred to the case of

Bateman V Hunt [1904]2 K. B. 530

"…if under his hand and seal a man asserts a think to be, he can not set up the contrary in any litigation between him and other party to that deed. Both parties are bound by the language of the deed and so are all claiming under them…"

Counsel for the Plaintiff in rebutted submitted that no reliance can be made on the settlement of 1999 because the Defendant also undertook to withdraw criminal charges against the Plaintiff which he did not.

I have reviewed the submissions of both parties on this issue and the evidence adduced in court.

It is clear from the evidence that all the parties were involved in some kind of business dealings which involved the granting of credit on some form of deferred payment. The exact nature of their business was not fully spoken to during the trial. That notwithstanding court can deduce from the documents on file that from as far back as the 21st October, 1994 the parties (i.e. the Plaintiff and the third parties) had already started setting accounts between them by signing a document entitled "Acknowledgment of indebtedness and undertaking to pay"; which they even registered with the Registrar of Documents.

It would appear that this undertaking of 1994 inter alia was not fully honoured and has continued to haunt the parties to this day; and hence this case. It has also

clearly also led to high handiness with the parties involving the police resulting into several detentions in a bid to get payment and I dare also add, also to settle old scores.

Several other settlements have been signed one being n 1995 (Exh. P.3) and another in 1999 (Exh. P.5). To my mind the most striking one is that of 14th November 1999 that sought to bring their conflict to an end and also to terminate all litigation. Counsel for the Defendant pointed out to court that this settlement also included the sum of Ushs. 35,000,000/= being pursued in this case, because the Plaintiff had earlier tried to recover it in HCCS No. 133 of 1999. That case was dismissed with orders that each party bear their own costs by The Hon. Lady Justice C. Byamugisha on the 4th April 2000 because both parties had failed to comply with court orders at the pre-trial schedule conference. It is not unreasonable to assume that the settlement of November 1999 could have had a bearing on why HCCS No. 133 of 1999 was ultimately dismissed; though that agreement unfortunately was not brought to the attention of the learned Trial Judge.

I have perused the court file of HCCS No. 133 of 1999 and found the claim to be exactly the same as the one before me. Since it was not dismissed on the merits, it was technically possible to have it re-filed which is what happened in this case.

I am therefore inclined to agree with Counsel for the Defendant that by reason of the agreement of 14th November 1999 this dispute before court had been settled and it was agreed by the parties that litigation should cease.

In the case of

Muhammad Muhammad Al Hassan V Ibrahim Al Gasim HCCS 504 of

2005 (unreported)

I held that where parties to a dispute have reconciled themselves and have evidenced that settlement by agreement (as was done here) then court under Article 126(2) (e) of The Constitution of Uganda 1995 is bound to recognize and enforce that settlement. Such a settlement in my view is as a result of an ADR (Alternative dispute Resolution) mechanism which is then reduced into writing. I again applied the same principles in yet another case

Buildtrust Construction Ltd V Maitha Rugasira HCCS No. 288 of 2005 (unreported)

I see no reason to depart from those principles in this case. I do not agree with the submissions of counsel for the Plaintiff that because the criminal case against his client was not withdrawn it showed that the settlement of 1999 was breached. Far from it. Criminal unlike civil cases are not that easily withdrawn and in any event his client won the criminal case on "no case to answer" which was at an early stage.

I accordingly shall enforce the agreement of the 14th November 1999 between the parties. In any event court is bound under Section 33 of the Judicature Act to avoid a multiplicity of cases. The Plaintiff is clearly barred by the principles of estoppel from

denying the agreement of the 14th November 1999 and its efficacy. That being the case there is no need for me to answer the remaining issues for trial.

This case is hereby dismissed with costs to the Defendants.

Geoffrey Kiryabwire

JUDGE

Date: 18/03/08

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Universe Tankships Inc of Monrovia v International Transport Works Federation [1983] 1 AC 366

Case cited

Bateman v Hunt [1904] 2 K.B. 530

Case cited

Muhammad Muhammad Al Hassan v Ibrahim Al Gasim HCCS 504 of 2005 (unreported)

Case cited

Buildtrust Construction Ltd v Maitha Rugasira HCCS No. 288 of 2005 (unreported)

Case cited

Article 126(2)(e) Constitution of Uganda 1995

Legislation

Legislation referenced in the available case record.

Section 33 Judicature Act

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this JurisAssist collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.