Babisa Sentumu v Commissioner Land Registration (Miscellaneous Application No. 118 of 2021) [2021] UGHCLD 214 (12 November 2021)
- Citation
- [2021] UGHCLD 214
- Status
- Judgment
- Jurisdiction
- Uganda
- Court
- HC: Land Division (Uganda)
- Panel
- Katamba Nkwanga, J
- Case number
- Miscellaneous Application No. 118 of 2021
- Language
- English
More details
- Court
- HC: Land Division (Uganda)
- Panel
- Katamba Nkwanga, J
- Case number
- Miscellaneous Application No. 118 of 2021
- Language
- English
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the 1st Defendant wrongfully withheld the Plaintiff's certificate of title for six years, causing her significant inconvenience and loss of opportunity to use her property as security, transfer it, or sell it. The Defendant's actions, including denying possession of the title and frustrating settlement efforts, unnecessarily prolonged the litigation and deprived the Plaintiff of her rights. The court held that the Plaintiff was entitled to general damages to compensate for the inconvenience and loss suffered, and awarded her Ugx. 20,000,000/= as general damages, as well as costs of the suit.
Court disposition
judgment for the plaintiff
Orders
- The Plaintiff is awarded general damages of Ugx. 20,000,000/=.
- The Plaintiff is awarded costs of the suit.
02
Material facts
Parties
Babirye Sarah
PlaintiffUganda National Roads Authority
DefendantM/S Consulting Surveyors & Planners
DefendantAmounts and remedies
- General Damages Awarded: UGX 20,000,000
03
Procedural history
Posture
Civil Suit / Judgment
04
Questions and positions
Legal issues
- 01
Whether the Plaintiff is entitled to general damages for the period her certificate of title was withheld by the Defendants.
- 02
Whether the Plaintiff is entitled to costs of the suit.
Party arguments
- Applicant
- The Plaintiff argued that her certificate of title was withheld by the Defendants for six years, depriving her of the ability to use it as security for loans, transfer the land to her children, or sell part of the land. She claimed this caused her significant inconvenience and financial loss, and sought compensation of Ugx. 30,000,000/= for the loss and inconvenience suffered.
- Respondent
- The 1st Defendant contended that the 2nd Defendant was contracted to collect certificates of title for subdivision and registration in the 1st Defendant's name, and that delays were due to a new land administration system. The 1st Defendant denied liability for any loss suffered by the Plaintiff and asserted that the certificate was obtained for lawful purposes.
05
Court’s reasoning
Legal principles
- 01
Uganda Commercial Bank Vs Kigozi [2002] 1 EA 305
A plaintiff who suffers damage due to the wrongful act of the defendant must be put in the position he or she would have been if the wrong had not occurred.
- 02
Charles Acire Vs Myaana Engola, HCCS 143/1993; Kibimba Rice Ltd Vs Umar Salim, SCCA 17/1992; Hardley Vs Baxendale (1894) 9 Exch 341
General damages are awarded to make good the inconvenience or loss suffered by the plaintiff due to the actions of the defendant.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the 1st Defendant wrongfully withheld the Plaintiff's certificate of title for six years, causing her significant inconvenience and loss of opportunity to use her property as security, transfer it, or sell it. The Defendant's actions, including denying possession of the title and frustrating settlement efforts, unnecessarily prolonged the litigation and deprived the Plaintiff of her rights. The court held that the Plaintiff was entitled to general damages to compensate for the inconvenience and loss suffered, and awarded her Ugx. 20,000,000/= as general damages, as well as costs of the suit.
Obiter and limits
- The certificate of title was obtained for lawful purpose, however, the Plaintiff had a right to receive the title once the purpose for which it was taken was completed.
- The actions of the 1st Defendant not only deprived the Plaintiff her rights to the use of her property/certificate of title but also caused loss onto her for prosecuting this suit over a matter that did not need to be brought to court in the first place.
Court disposition
judgment for the plaintiff
- The Plaintiff is awarded general damages of Ugx. 20,000,000/=.
- The Plaintiff is awarded costs of the suit.
Source and reliance status
HC: Land Division (Uganda)
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
HC: Land Division (Uganda)
Judgment
THE REPUBLIC OF UGANDA
IN THE HIGH COURT OF UGANDA AT MASAKA
CIVIL SUIT NO. 71 OF 2016
BABIRYE SARAH ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: PLAINTIFF
VERSUS
1. UGANDA NATIONAL ROADS AUTHORITY
2. M/S CONSULTING SURVEYORS & PLANNERS ::::::::::::::::::: DEFENDANTS
*Before; Hon. Justice Victoria Nakintu Nkwanga Katamba*
JUDGMENT
The Plaintiff Babirye Sarah brought this suit against the Defendants jointly and severally for the return of a Certificate of Title for land comprised in Buddu Block 185 Plot 315 (the suit land) at Lukaya Town Council, Kalungu District, general damages and costs of the suit.
The Plaintiff's claim is that she is the registered proprietor for the suit land and during the construction of the Kamengo-Lukaya Masaka Highway, the 1st Defendant used a portion of the suit land and requested the Plaintiff to hand over the certificate of title to the land for purposes of valuation. The certificate of title was received on the 25/11/2013 and has not been returned to date despite the Plaintiff's demands for the same.
In its Written Statement of Defense, the 1st Defendant denied the Plaintiff's claim and averred that the 2nd Defendant was contracted to identify and assess property that was likely to be affected by the construction. The 2nd Defendant collected certificates of title including the Plaintiff`s title for subdivision and registration in the 1st Defendant's name. The registration process has been delayed due the new land administration and management system and the 1st Defendant is not liable for any loss suffered by the Plaintiff.
When the matter proceeded for hearing on the 1st day of July, 2020, counsel for the Plaintiff informed court that the Plaintiff's certificate of title had been returned and the only issue to determine related to damages. On the 9th day of September, 2020, parties informed court that they reached a settlement and court gave an adjournment for production of a settlement to be endorsed by court. The settlement was never produced and the Plaintiff gave her evidence on damages.
The Plaintiff stated that her certificate of title was taken on 25th November, 2013 and returned on the 26th November, 2019 after the institution of this suit. She was deprived from using her title as security to borrow money and she could not transfer her land to her children. She was also unable to sell part of the land and upon receipt of the title, she was finally able to obtain a loan and pay her medical treatment costs. The Plaintiff prayed for compensation from the 1st Defendant for the time she was deprived of her title and prayed for damages of Ugx. 30,000,000/= for the loss and inconvenience suffered.
In cross examination, she stated that she was compensated for the land that was acquired by the 1st Defendant but the compensation did not include disturbance allowance. The Parties had agreed to a settlement of Ugx. 5,000,000/= but the 1st Defendant never showed and she accepted the 5,000,000/= because she is sick and did not want to waste court's time.
Determination of the suit;
The only issue for determination relates to damages. In assessment of the quantum of damages, courts are mainly guided by the value of the subject matter, the economic inconvenience that a party may have been put through and the nature and extent of the breach or injury suffered and a plaintiff who suffers damage due to the wrongful act of the Defendant must be put in the position he or she would have been if she or he had not suffered the wrong*. (See Uganda Commercial Bank Vs Kigozi [2002] 1 EA 305, Charles Acire Vs Myaana Engola, HCCS 143/1993, Kibimba Rice Ltd Vs Umar Salim, SCCA 17/1992 and Hardley Vs Baxendale (1894) 9 Exch 341)*
The purpose of general damages is to make good of the inconvenience or loss suffered by the Plaintiff due to the actions of the Defendant. In the instant case, the 1st Defendant held onto the Plaintiff`s certificate of title for a period of six years. The Plaintiff wrote letters to the 1st Defendant to retrieve her title which course of action should have solved this entire case had the 1st Defendant returned the certificate of title.
The certificate of title was obtained for lawful purpose, however, the Plaintiff had a right to receive the title once the purpose for which it was taken was completed.
Furthermore, in its Written Statement of Defence, the 1st Defendant denied the claim yet the certificate of title was in its possession. The 1st Defendant instead of acknowledging its mistake, and saving this court time, chose to drag on a case that was filed in 2016 and in addition, attempted to settle the case with the Plaintiff and frustrated the settlement process on several occasions.
The actions of the 1st Defendant therefore not only deprived the Plaintiff her rights to the use of her property/certificate of title but also caused loss onto her for prosecuting this suit over a matter that did not need to be brought to court in the first place.
The Plaintiff stated that she was inconvenienced from dealing in her land, using her land as security and transferring the land to her children. The Plaintiff adduced evidence that she was able to obtain a loan upon receipt of her certificate of title.
I therefore find that the Plaintiff was indeed inconvenienced by the wrongful actions of the 1 st Defendant and will therefore award general damages of Ugx. 20,000,000/=
Judgment is hereby entered for the Plaintiff and the Plaintiff is awarded costs of the suit.
I so order.
Dated at Masaka this 17th day of January, 2022
Signed;
Victoria Nakintu Nkwanga Katamba