Share
Archstone Solutions Ltd v Mutukula Regional Market Ltd and Karamagi Karim (Civil Suit 316 of 2024) [2025] UGCommC 113 (30 April 2025)
- Citation
- [2025] UGCommC 113
- Status
- Judgment
- Jurisdiction
- Uganda
- Court
- Commercial Court of Uganda
- Panel
- Susan Odongo, J
- Case number
- Civil Suit 316 of 2024
- Language
- English
More details
- Court
- Commercial Court of Uganda
- Panel
- Susan Odongo, J
- Case number
- Civil Suit 316 of 2024
- Language
- English
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court determined that the Special Conditions Clause 25.4 of the contract, which provides for arbitration in accordance with the Arbitration and Conciliation Act, prevails over the general dispute resolution clause. The inclusion of an arbitration clause indicates the parties' intention for disputes to be resolved by arbitration, and courts must respect this choice. As such, the court's jurisdiction is ousted, and the matter must be referred to arbitration. The suit is therefore stayed and referred to arbitration, with each party bearing its own costs.
Court disposition
suit stayed and referred to arbitration
Orders
- Civil Suit 0316 of 2024 is stayed and referred to Arbitration in accordance with section 5 of the Arbitration Conciliation Act Cap. 5.
- Each party bears its own costs.
02
Material facts
Parties
Archstone Solutions Ltd
PlaintiffMutukula Regional Market Ltd
DefendantKaramagi Karim
DefendantAmounts and remedies
- Contract Price: UGX 1,347,900,000
- Amount Paid: UGX 66,000,000
- Claimed Balance: UGX 206,000,000
03
Procedural history
Posture
Civil Suit / Judgment
04
Questions and positions
Legal issues
- 01
Whether the dispute between the parties should be resolved by arbitration or by court as per the contract provisions.
- 02
Which dispute resolution clause in the contract prevails: the general agreement or the special conditions clause.
- 03
Whether the court has jurisdiction to entertain the suit in light of the arbitration agreement.
Party arguments
- Applicant
- The Defendants argued that they were only indebted to the Plaintiff in the sum of Ugx 34,000,000/=, not Ugx 206,000,000/=. They claimed the contract price was Ugx 100,000,000/=, of which Ugx 66,000,000/= had already been paid, leaving a balance of Ugx 34,000,000/=. They sought unconditional leave to appear and defend the summary suit, disputing the liquidated sum and asserting a good defense. No contract reflecting their position was attached.
- Respondent
- The Plaintiff maintained the claim for Ugx 206,000,000/=, attached the agreement reflecting the contract price, and prayed for dismissal of the Defendants' application with costs. The Plaintiff further requested judgment in the summary suit for the liquidated sum and argued that clause 7 of the agreement allowed dispute resolution by either arbitration or court, at the aggrieved party's option. The Plaintiff noted prior failed mediation and doubted arbitration would resolve the matter.
05
Court’s reasoning
Legal principles
- 01
General principles of contract law; referenced in judgment.
Special Conditions in a contract take precedence over General Conditions when there is inconsistency, as they reflect the negotiated and agreed position of the parties.
- 02
Section 5 of the Arbitration and Conciliation Act, Cap. 4; Melford Capital Partners, LLP and Others Vs. Frederick Digby (England and Wales High Court (Chancery Division April 19, 2021)).
Where parties agree to arbitration as a dispute resolution mechanism, courts must respect that choice and refer disputes to arbitration, thereby ousting the court's jurisdiction.
06
Ratio, limits and disposition
Ratio decidendi
The court determined that the Special Conditions Clause 25.4 of the contract, which provides for arbitration in accordance with the Arbitration and Conciliation Act, prevails over the general dispute resolution clause. The inclusion of an arbitration clause indicates the parties' intention for disputes to be resolved by arbitration, and courts must respect this choice. As such, the court's jurisdiction is ousted, and the matter must be referred to arbitration. The suit is therefore stayed and referred to arbitration, with each party bearing its own costs.
Obiter and limits
- Standard Form Contracts often contain precedence clauses to resolve inconsistencies between general and special conditions.
- Courts adopt a harmonious approach to interpreting dispute resolution clauses, recognizing the validity and independence of arbitration agreements.
- Arbitration clauses retain their effect unless there is compelling language to render them meaningless.
Court disposition
suit stayed and referred to arbitration
- Civil Suit 0316 of 2024 is stayed and referred to Arbitration in accordance with section 5 of the Arbitration Conciliation Act Cap. 5.
- Each party bears its own costs.
Source and reliance status
Commercial Court of Uganda
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
Commercial Court of Uganda
Judgment
THE REPUBLIC OF UGANDA INTHE HIGH COURT OF UGANDA AT KAMPALA (COMMERCIAL DIVISION) HIGH COURT CIVIL SUIT 0316 OF 2024
ARCHSTONE SOLUTIONS LTD…………………………. PLAINTIFF
VERSUS
1. MUTUKULA REGIONAL MARKET LTD.....................DEFENDANTS
2. KARAMAGI KARIM
BEFORE: HON. LADY JUSTICE SUSAN ODONGO
JUDGMENT
The background to this matter is that:
On 1st May 2021, the Plaintiff and the 1st Defendant executed an agreement wherein the 1st Defendant contracted the Plaintiff to construct a market yard to gravel standard for Mutukula Regional Market at Mutukula. The contract price was agreed at Ugx 1,347,900,000/=. The agreed payment schedule stated that payment for all the works carried out on site would be made after 14 working days of approval of certificate by project engineers; and the 1 st Defendant would effect payment within 30 days from certification.
The 1st Defendant has since paid the Plaintiff Ugx 66,000,000/ leaving a balance of Ugx 206,000,000/-. The 2nd Defendant issued to the Plaintiff bank cheques but the same were dishonoured by the bank for insufficiency of funds.

The Plaintiff then filed this summary suit, for the liquidated sum, under Order 36 of the Civil Procedure Rules, S. I. 171-1. The Defendants filed an Application for unconditional leave to appear and defend the summary suit disputing the liquidated sum and stating that they have a good defense to the suit. In the Affidavit in support, the Defendants/Applicants denied being indebted to the Plaintiff/Respondent to the alleged sum of Ugx 206,000,000/= but rather to a sum of Ugx 34,000,000/=. According to the Defendants/Applicants they had agreed that they would pay the Plaintiff/Respondent Ugx 100,000,000/= for the works. That they had paid the Plaintiff/Respondent Ugx 66,000,000/=leaving a balance of Ugx 34,000,000/=. The Defendants/Applicants did not attach the contract which reflects this position.
The Plaintiff/Respondent filed an affidavit in reply by which he reiterated the claim in the summary plaint, attached the agreement and prayed that the Application is dismissed with costs.
When the Application came up for hearing, the Defendants/Applicants did not appear, the Plaintiff/Respondent was in Court. Upon the application of the Plaintiff/Respondent, the application was dismissed with costs to thePlaintiff/Respondent.
The Plaintiff/Respondent in addition prayed that the Court enter judgment in the summary suit for the liquidated sum. This Court brought it to the attention of the Plaintiff/Respondent that there are competing dispute resolution agreements in the contract.
According to clause 7 of the Agreement the dispute settlement provision states:
*"In event of any dispute between the parties arising from this agreement, such dispute (if not resolved by mutual agreement within 30 days)shall be referred for arbitration or courts of law governed by the Laws of Uganda, whicheverthe aggrieved party may choose".*

The Special Conditions Clause 25.1 states that the procedure for disputes shall be as specified in GCC 25.2 to 25.4. Special Conditions Clause 25.4 provides for the dispute settlement mechanism to be by *Arbitration conducted in accordance with the Arbitration and Conciliation Act, 2000 of Uganda and the place of Arbitration agreed as Kampala, Uganda.*
At the hearing, the Plaintiff/Respondent implored the Court to rely on clause 7 of the Agreement which provided the dispute settlement mechanism to be either by arbitration or by court, at the option of the aggrieved party. He further submitted that the parties had previously been to mediation but had failed to amicably resolve the matter. The Plaintiff/Respondent expressed doubtfulness that arbitration would resolve the matter.
The Decision:
Standard Form Contracts like the one the parties concluded comprising; an Agreement, the General Conditions and the Special Conditions, are typically used in construction projects which require extensive detail. For proper reading, parties often insert a 'Precedence Clause' to address conflict such as the one before this court. To the extent that, in the event of any inconsistency the parties would have expressly agreed to which document in the Contract prevails.
Special Conditions are negotiated to address specific situations, and therefore are considered more specific and intentional providing clarity in case of ambiguity or uncertainty. In most legal and contractual frameworks, unless otherwise expressly agreed, if there is a disagreement between the Standard Contract and the Special Conditions Clause, the Special Condition Clause usually takes precedence because they are considered more reflective of the negotiated and agreed position of the parties to the Contract.

With particular regard to dispute resolution provisions, Courts respect the parties' choice of dispute resolution mechanism. Where parties agree to a dispute resolution mechanism outside of Court, it ousts the jurisdiction of the Court. In cases where the agreement contains both Arbitration and/or Court as a dispute resolution mechanism, rather than dismissing the arbitration clause, the Court adopts a practical approach, by reading these clauses in harmony, rather than in conflict with each other, recognizing the arbitration clause as a valid and independent agreement while interpreting the other alternative as allowing the Court to oversee the arbitration process. Inclusion of an arbitration clause by parties infers that they intended it to have effect and were unwilling to render it meaningless. Arbitration clauses retain their validity unless language compels the conclusion that the parties, having gone to the trouble of inserting a broad arbitration clause, intended to eviscerate the clause almost entirely by preceding it with a service of suit clause. *(Melford Capital Partners, LLP and Others Vs. Frederick Digby (England and Wales High Court (Chancery Division April 19, 2021)).*
In light of the foregoing, I find that the arbitration agreement in the Special Conditions Clause 25.4 prevails, is operative and capable of being performed.
I hereby make the following orders:
- 1. Civil Suit 0316 of 2024 is stayed and referred to Arbitration in accordance with section 5 of the Arbitration Conciliation Act Cap. 5. - 2. Each party bears its own costs.
Dated, signed and delivered electronically this 30th day of April 2025.

Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.